1,456MW coal-fired power plant plus jetty.  Fuel advisory, PPA, and modelling.
2,063MW Net Capacity coal-fired power plant.  Financial modelling, fuel source analysis, plant operations review, and PPA negotiations.
80MW open-cycle turbine located at a gasfield transmitting to a mine load. Condensate fuel backup.
44 MW cogeneration using steam-injection on peak. Specified the engineering and insurance reviews for financing.
12 MW open-cycle plant with 26km gas spurline. Full turnkey workup, site/easement acquisition, and O&M support
4.6 MW reciprocating engine island power plant, including upgrade through transmission and distribution.
345 MW combined-cycle gas turbine plant, with particular emphasis on tariff structure and financability.
Scoping and review of nine power and cogen options for 10 MW load.
Comparison of gas, distillate, and coal configurations.15 MW methane-drainage turbine plant (coal mine) including fuel gas treatment and compression.
24 MW combined-cycle power plant using oil refinery high-hydrogen off-gases.
PPA with refinery and state utility.66 MW barge-mounted diesel sets requiring political-risk insurance. PPA partly indexed to customer's price index.21-year coal supply agreement negotiations.
Mediation on escalation methodologies and force majeure clauses.
6 MW single turbine for high pressure steam, with utility standby.
27 MW open-cycle utility power station, dual-fuelled, designed for fully automatic system operation.
15 MW open-cycle turbine plant, including fuelgas treatment supporting industrial and utility loads at 22 KV and 66 KV.
104 MW combined cycle turbine plant with chillers. Export credit and local currency financing.
2x30 MW and 2x60 MW coal-fired power plants as refurbish-own-operate joint venture
350 MW island plant servicing industrial development on a BOO facility
2,100MW, the world's largest IPP, where the main issues are the PPA fit to the equipment, tariff, and financing
 